The current project schedule involves meeting funding agency startup requirements, so the District can execute contracts with the various funding agencies and access funds to begin work, along with initiating and completing the hydrogeologic assessment.
| TASK | MONTH / YEAR | |
|---|---|---|
| Meet Awarded Grant Startup Conditions | January 2020 | |
| Hydrogeologic Assessment | 2020 | |
| DEQ Submittal for Construction of Wells | April 2026 | |
| CDBG Environmental Assessment | April/May 2026 | |
| Project Bidding for Wells | May 2026 | |
| Project Construction for Wells | May/June 2026 |
The project schedule aligns with multiple funding agency requirements and is subject to change.